Infrastructure Updates

Infrastructure Updates
Infrastructure Updates

500,000 GALLON ELEVATED WATER STORAGE TANK

  1. Project Start Date:  August 2022
  2. Original Bid Date:  September 2023
  3. Geotechnical Soil Borings put on hold in: February 2023 (2 month delay – tank style decision)
  4. Scope Increase: After the initial Study Phase project scope expanded to 5 locations:
  • Junny Road Tank Site
  • Kennebec Church Road Tank Site (piping modifications and removal of the booster station)
  • Junny Road Standpipe (demolition)
  • Dora Street Elevated Tank Site (demolition)
  • Booster Station Site (Tippett Road – 7 months to locate and acquire the property – January 2023 to July 2023 authorization to proceed with design)
  1. Public Water Supply Permit Submittal: November 2023
  2. Division of Water Infrastructure Submittal: March 2024
  3. Updated Bid Date: May 2024
  4. Project Completion: December 2025 (19 month construction)

CORE WATER SYSTEM REPLACEMENT PROJECT (8.1 miles)

  1. Permit Submittal Date: June 2024
  2. Begin Construction: March 2024
  3. Project Completion: September 2026
  4. Currently on schedule

MM#3 – SOUTH BROAD STREET CULVERT REPLACEMENT

  1. Began Design: March 2023
  2. CSX Property Inquiry Request:  May 2023
  3. Project Hold: May 2023
  4. CSX Reverted Parcel to Adjacent Landowners
  5. Working to acquire additional ROW.
  6. Permit Time: 4 Months
  7. Construction Time: 3 Months