Infrastructure Updates
Posted on: November 1, 2023 - 10:24am
500,000 GALLON ELEVATED WATER STORAGE TANK
- Project Start Date: August 2022
- Original Bid Date: September 2023
- Geotechnical Soil Borings put on hold in: February 2023 (2 month delay – tank style decision)
- Scope Increase: After the initial Study Phase project scope expanded to 5 locations:
- Junny Road Tank Site
- Kennebec Church Road Tank Site (piping modifications and removal of the booster station)
- Junny Road Standpipe (demolition)
- Dora Street Elevated Tank Site (demolition)
- Booster Station Site (Tippett Road – 7 months to locate and acquire the property – January 2023 to July 2023 authorization to proceed with design)
- Public Water Supply Permit Submittal: November 2023
- Division of Water Infrastructure Submittal: March 2024
- Updated Bid Date: May 2024
- Project Completion: December 2025 (19 month construction)
CORE WATER SYSTEM REPLACEMENT PROJECT (8.1 miles)
- Permit Submittal Date: June 2024
- Begin Construction: March 2024
- Project Completion: September 2026
- Currently on schedule
MM#3 – SOUTH BROAD STREET CULVERT REPLACEMENT
- Began Design: March 2023
- CSX Property Inquiry Request: May 2023
- Project Hold: May 2023
- CSX Reverted Parcel to Adjacent Landowners
- Working to acquire additional ROW.
- Permit Time: 4 Months
- Construction Time: 3 Months